(a) A contractor or subcontractor may elect not to proceed with additional work directed by an owner if:
(1) the contractor or subcontractor has not received a written, fully executed change order for the owner-directed additional work; and
(2) the aggregate actual or anticipated value of the additional work plus any previous owner-directed additional work for which the contractor or subcontractor has not received a written, fully executed change order exceeds 10 percent of the contractor's or subcontractor's original contract amount.
(b) A contractor or subcontractor who elects not to proceed with additional work as provided by this section is not responsible for damages associated with the election not to proceed.
Cite this article: FindLaw.com - Texas Property Code - PROP § 28.0091. Unsigned Change Order - last updated January 01, 2024 | https://codes.findlaw.com/tx/property-code/prop-sect-28-0091/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)