Current as of January 01, 2024 | Updated by Findlaw Staff
A. The secretary may use a construction manager general contractor delivery method on a project if the department makes a written determination that it is appropriate and in the best interest of the department to use this method of project delivery to procure an eligible project. The determination to use the construction manager general contractor delivery method shall be issued only after the department considers the following criteria, at a minimum:
(1) the level of design and the extent to which the project requirements have been or can be adequately defined;
(2) time constraints for project delivery;
(3) project complexity;
(4) the suitability of use of the construction manager general contractor delivery method; and
(5) the capability of the department to manage the project, including experienced personnel or outside consultants.
B. The secretary shall not make a determination to use a construction manager general contractor delivery method unless the project is posted with such determination on the department's website for at least ninety days.
C. The secretary, in consultation with the professional associations and contractors from within the highway design and construction industry, shall promulgate rules for solicitation and award of construction manager general contractor contracts. The rules shall establish criteria for selecting, procuring and contracting a project using the construction manager general contractor delivery method. The rules shall define the scope of the construction manager general contractor contract to require the construction manager general contractor to:
(1) provide a range of preconstruction services and participate in project design, cost control, scheduling and value engineering efforts for the project; and
(2) if the second phase of the contract is entered into, provide the construction work for the project or work packages associated with the project at a guaranteed maximum price for which the construction manager general contractor is financially responsible.
Cite this article: FindLaw.com - New Mexico Statutes Chapter 13. Public Purchases and Property § 13-1-122.3. Construction manager general contractor delivery method authorized - last updated January 01, 2024 | https://codes.findlaw.com/nm/chapter-13-public-purchases-and-property/nm-st-sect-13-1-122-3/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)