(1) Before the construction manager begins any construction services, a contracting agency shall:
(a) Conduct an independent cost estimate for the project; and
(b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.
(2) If the construction manager and the contracting agency are unable to negotiate a contract, the contracting agency may use other contract procurement processes. Persons or organizations who submitted proposals but were unable to negotiate a contract with the contracting agency shall be eligible to compete in the other contract procurement processes.
Cite this article: FindLaw.com - Nebraska Revised Statutes Chapter 39. Highways and Bridges § 39-2820. Contracting agency; cost estimate; conduct contract negotiations - last updated January 01, 2024 | https://codes.findlaw.com/ne/chapter-39-highways-and-bridges/ne-rev-st-sect-39-2820/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)