(1) Construction managers shall submit proposals as required by the request for proposals.
(2) Proposals shall be sealed and shall not be opened until expiration of the time established for making the proposals as set forth in the request for proposals.
(3) Proposals may be withdrawn at any time prior to signing a contract for preconstruction services. The contracting agency shall have the right to reject any and all proposals at no cost to the contracting agency. The contracting agency may thereafter solicit new proposals or may cancel the construction manager-general contractor procurement process.
(4) The contracting agency shall rank the construction managers in accordance with the qualification-based selection process and pursuant to the criteria in the request for proposals. The contracting agency may meet with construction managers prior to the ranking.
(5) The contracting agency may attempt to negotiate a contract for preconstruction services with the highest ranked construction manager and may enter into a contract for preconstruction services after negotiations. If the contracting agency is unable to negotiate a satisfactory contract for preconstruction services with the highest ranked construction manager, the contracting agency may terminate negotiations with that construction manager. The contracting agency may then undertake negotiations with the second highest ranked construction manager and may enter into a contract for preconstruction services after negotiations. If the contracting agency is unable to negotiate a satisfactory contract with the second highest ranked construction manager, the contracting agency may undertake negotiations with the third highest ranked construction manager, if any, and may enter into a contract for preconstruction services after negotiations.
(6) If the contracting agency is unable to negotiate a satisfactory contract for preconstruction services with any of the ranked construction managers, the contracting agency may either revise the request for proposals and solicit new proposals or cancel the construction manager-general contractor contract process under sections 39-2808 to 39-2824.
Cite this article: FindLaw.com - Nebraska Revised Statutes Chapter 39. Highways and Bridges § 39-2819. Submission of proposals; sealed; rank of construction managers; negotiation of contract - last updated January 01, 2024 | https://codes.findlaw.com/ne/chapter-39-highways-and-bridges/ne-rev-st-sect-39-2819/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)