1. An owner may apply to the board for a written determination regarding whether a facility is a qualified facility by submitting to the board a written application containing all of the following:
a. Information regarding the ownership of the facility including the percentage of equity interest held by each owner.
b. The nameplate generating capacity of the facility.
c. Information regarding the facility's initial placement in service.
d. Information regarding the type of facility.
e. Except when electricity is used for on-site consumption, a copy of an executed power purchase agreement or other agreement to purchase electricity upon completion of the project. An executed interconnection agreement or transmission service agreement shall be accepted by the board under this paragraph if the owner of the facility has agreed to sell electricity from the facility directly or indirectly to a wholesale power pool market.
f. Any other information the board may require.
2. The board shall review the application and supporting information and shall make a preliminary determination regarding whether the facility is a qualified facility. The board shall notify the applicant of the approval or denial of the application within thirty days of receipt of the application and information required. If the board fails to notify the applicant of the approval or denial within thirty days, the application shall be deemed denied. An applicant who receives a determination denying an application may file an appeal with the board within thirty days from the date of the denial pursuant to the provisions of chapter 17A. In the absence of a timely appeal, the preliminary determination shall be final. If the application is incomplete, the board may grant an extension of time for the provision of additional information.
3. A facility that is not operational within eighteen months after issuance of an approval for the facility by the board shall cease to be a qualified facility. However, a facility that is approved as qualified under this section but is not operational within eighteen months due to the unavailability of necessary equipment shall be granted an additional twelve months to become operational. A facility that is granted and thereafter loses approval may reapply to the board for a new determination.
4. The maximum amount of nameplate generating capacity of all qualified facilities the board may find eligible under this chapter shall not exceed fifty megawatts of nameplate generating capacity.
5. An owner shall not be an owner of more than two qualified facilities.
Cite this article: FindLaw.com - Iowa Code Title XI. Natural Resources [Chs. 455-485] § 476B.5. Determination of eligibility - last updated January 01, 2024 | https://codes.findlaw.com/ia/title-xi-natural-resources-chs-455-485/ia-code-sect-476b-5/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)