Current as of March 28, 2024 | Updated by FindLaw Staff
(a) In determining whether a certificate of public convenience and necessity shall be granted, the commission must consider the following:
(1) Whether existing gas pipelines or distribution systems are adequate to meet the reasonable public needs;
(2) The volume of demand for such gas, and whether such demand and that reasonably to be anticipated in the future can support already existing gas pipeline and distribution systems, if any, and also the pipeline or distribution system proposed by the applicant;
(3) The financial ability of the applicant to furnish adequate continuous service and to meet the financial obligations of the service which the applicant proposes to perform;
(4) The adequacy of the supply of gas to serve the public;
(5) The economic feasibility of the pipeline or distribution system and the propriety of the engineering and contracting fees, the expenses, and the financing charges and costs connected with the pipeline or distribution system; and
(6) The effect on existing revenues and service of other pipelines or distribution systems, and particularly whether the granting of the certificate will or may seriously impair existing public service.
(b) This Code section shall not be construed as exhaustively describing all factors which the commission may consider in its decision to grant or deny a certificate.
(c) If the applicant seeks a certificate of public convenience and necessity authorizing the applicant to acquire a gas pipeline or distribution system of a municipal corporation, the commission shall also consider whether the purchase price is reasonable in light of the present value of the system to be acquired. Issuance by the commission of a certificate of public convenience and necessity authorizing such acquisition is a determination by the commission, among other things, that the purchase price is the measure of the value of the system to be included in the applicant's rate base for rate-making purposes, subject to the depreciation thereafter allowed upon such system.
Cite this article: FindLaw.com - Georgia Code Title 46. Public Utilities and Public Transportation § 46-4-25 - last updated March 28, 2024 | https://codes.findlaw.com/ga/title-46-public-utilities-and-public-transportation/ga-code-sect-46-4-25/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)