Current as of January 01, 2024 | Updated by Findlaw Staff
(a) Proposals shall be submitted in two separate, clearly identified, sealed packages, with the first containing the technical submission and the second containing the cost submission. If the technical submission and cost submission are not submitted in two separate, clearly identified sealed packages, the Board shall disqualify the submission.
(b) Proposals may not be opened until expiration of the time established for making proposals as set forth in the invitation for proposals.
(c) The design-builder shall furnish a bid bond not to exceed five percent of the maximum cost of the design-build contract. In the event the proposal is accepted and the design-builder fails to execute the design-build contract, the bid bond will be forfeited.
(d) To the extent required in the invitation for proposal, the design-builder shall identify each firm to whom the design-builder proposes to sublet obligations under the design-build contract. At a minimum, the design-builder shall identify each firm responsible for the design and primary construction and their affiliation to the design-builder.
(e) The design-builder shall specify in the proposal the cost of the design-build contract that will not be exceeded if the proposal is accepted without change. After award of the proposal, the maximum cost of the proposal may be converted to fixed prices by negotiated agreement between the agency and the design-builder.
(f) Prior to the award of the design-build contract, all drawings, specifications and other information submitted in the proposal shall remain the property of the design-builder submitting the proposal. Additionally, prior to the award of the design-build contract, the agency shall maintain the secrecy and confidentiality of all information contained in the proposal. Once a proposal is accepted, the disclosure of the proposal and the information in the proposal, and the ownership of the drawings, specifications and information therein, shall be determined in accordance with existing law and the terms of the design-build contract.
(g) Proposals may not be amended during the review process.
(h) At the discretion of the agency, a stipend may be paid to the design-builders not ultimately selected.
Cite this article: FindLaw.com - West Virginia Code Chapter 5. General Powers and Authority of the Governor, Secretary of State and Attorney General; Board of Public Works; Miscellaneous Agencies, Commissions, Offices, Programs, Etc. § 5-22A-11. Proposals - last updated January 01, 2024 | https://codes.findlaw.com/wv/chapter-5-general-powers-and-authority-of-the-governor-secretary-of-state-and-attorney-general-board-of-public-works-miscellaneous-agencies-commissions-offices-programs-etc/wv-code-sect-5-22a-11/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)