(a) This section applies to coal electric generation facilities as identified and communicated to the Secretary by the West Virginia Department of Economic Development as sites that may be suitable for one or more coal electric generation facilities in accordance with § 5B-2O-1 et seq. of this code, or as identified by an applicant for a construction and operating permit for one or more coal electric generation facilities.
(b) The secretary shall take all reasonable steps to expedite consideration of permit applications utilizing sites designated by the Department of Economic Development as a site suitable for use as a coal electric generation facility and communicated to the secretary in accordance with § 5B-2O-1 et seq. of this code. Such steps shall include:
(1) An initial determination of whether the identified site is in compliance with National Ambient Air Quality Standards and the West Virginia State Implementation Plan, whether emissions from a coal electric generation facility would be likely to interfere with compliance with the same and, if interference is likely, the steps necessary to avoid noncompliance with National Ambient Air Quality Standards and the State Implementation Plan; and
(2) Evaluation of whether there is sufficient data, meteorological and otherwise, that would allow acceptable modeling of the impacts of emissions from a coal electric generation facility, and if not, construction of sampling and measuring devices to acquire such data at the site.
(c) Unless otherwise specifically provided in this article, the secretary shall issue a permit for a coal electric generation facility which is determined to be a major stationary source within a reasonable time, not to exceed 270 calendar days, after the secretary determines that the application is complete. The secretary must determine whether an application is complete within 30 days from the date the permit application is filed with the secretary and communicated to the permit applicant.
Cite this article: FindLaw.com - West Virginia Code Chapter 22. Environmental Resources § 22-5-11c. Construction and operating permits required for coal electric generation facilities as stationary sources of air pollutants - last updated January 01, 2024 | https://codes.findlaw.com/wv/chapter-22-environmental-resources/wv-code-sect-22-5-11c/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)