Current as of May 05, 2022 | Updated by FindLaw Staff
Welcome to FindLaw's Cases & Codes, a free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
(1) Except as provided in Subsection (3), the board may not expend money for construction costs for any phase of the project until:
(a) the board has contracted with the districts for the sale of at least 70% of the water developed by that phase of the project; and
(b) all permits required by the environmental impact statement have been obtained.
(2) Construction of the project and implementation of any environmental mitigation requirements may proceed concurrently.
(3) The board may make expenditures for preconstruction costs if money is expressly appropriated or earmarked by statute for that purpose by the Legislature.
Cite this article: FindLaw.com - Utah Code Title 73. Water and Irrigation § 73-28-202. Construction contingent upon sale of water - last updated May 05, 2022 | https://codes.findlaw.com/ut/title-73-water-and-irrigation/ut-code-sect-73-28-202/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.