As used in this chapter:
(1) “Affected entity” means an entity as defined in Sections 10-9a-103 and 17-27a-103.
(2) “Affected landowner” means an owner of a property interest, as reflected in the most recent county or city tax records as receiving a property tax notice, whose property is located within a proposed corridor.
(3)(a) “Construction” means the excavation, construction, and installation of a high voltage electric power line or upgraded high voltage transmission line.
(b) “Construction” does not include:
(i) the temporary use of sites; or
(ii) studies and tests for:
(A) requirements of this chapter;
(B) state regulations;
(C) federal regulations;
(D) securing geological and survey data; or
(E) any other actions taken by a public utility reasonably necessary to determine the location of a target study area or proposed corridor.
(4) “High voltage power line” means:
(a) an electrical high voltage power line with a nominal voltage of 230 kilovolts or more; and
(b) an upgraded high voltage power line.
(5) “Land use application” has the same meaning as provided in Sections 10-9a-103 and 17-27a-103.
(6) “Land use authority” has the same meaning as provided in Sections 10-9a-103 and 17-27a-103.
(7) “Land use permit” has the same meaning as Sections 10-9a-103 and 17-27a-103.
(8) “Legislative body” has the same meaning as provided in Sections 10-9a-103 and 17-27a-103.
(9) “Proposed corridor” means the transmission line route within a target study area selected by the public utility as the public utility's proposed alignment for a high voltage power line.
(10) “Proposed route” means the right-of-way needed for construction of the high voltage power line.
(11) “Public utility” has the same meaning as provided in Section 54-2-1.
(12) “Target study area” means the geographic area for a new high voltage transmission line or an upgraded high voltage power line as proposed by a public utility.
(13) “Upgraded high voltage power line” means increasing the voltage of an existing transmission line to 230 kilovolts or more.
Cite this article: FindLaw.com - Utah Code Title 54. Public Utilities § 54-18-102. Definitions - last updated May 05, 2022 | https://codes.findlaw.com/ut/title-54-public-utilities/ut-code-sect-54-18-102/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)