Skip to main content

Texas Property Code - PROP § 53.101. Required Retainage

Welcome to FindLaw's Cases & Codes, a free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.

(a) During the progress of work under an original contract for which a mechanic's lien may be claimed and for 30 days after the work is completed, the owner shall retain:

(1) 10 percent of the contract price of the work to the owner;  or

(2) 10 percent of the value of the work, measured by the proportion that the work done bears to the work to be done, using the contract price or, if there is no contract price, using the reasonable value of the completed work.

(b) In this section, “owner” includes the owner's agent, trustee, or receiver.

Cite this article: FindLaw.com - Texas Property Code - PROP § 53.101. Required Retainage - last updated April 14, 2021 | https://codes.findlaw.com/tx/property-code/prop-sect-53-101/


FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.