(a) A municipality shall process each permit application on a nondiscriminatory basis.
(b) Not later than the 30th day after the date the municipality receives an application for a permit for a network node or node support pole, or the 10th day after the date the municipality receives an application for a permit for a transport facility, the municipality shall determine whether the application is complete and notify the applicant of that determination. If the municipality determines that the application is not complete, the municipality shall specifically identify the missing information.
(c) A municipality shall approve an application that does not require zoning or land use approval under this chapter unless the application or the corresponding work to be performed under the permit does not comply with the municipality's applicable codes or other municipal rules, regulations, or other law that is consistent with this chapter.
(d) A municipality must approve or deny an application for a node support pole not later than the 150th day after the date the municipality receives the complete application. A municipality must approve or deny an application for a network node not later than the 60th day after the date the municipality receives the complete application. A municipality must approve or deny an application for a transport facility not later than the 21st day after the date the municipality receives a complete application. An application for a permit for a node support pole, network node, or transport facility shall be deemed approved if the application is not approved or denied on or before the applicable date for approval or denial prescribed by this subsection.
(e) A municipality that denies a complete application must document the basis for the denial, including the specific applicable code provisions or other municipal rules, regulations, or other law on which the denial was based. The municipality shall send the documentation by electronic mail to the applicant on or before the date the municipality denies the application.
(f) Not later than the 30th day after the date the municipality denies the application, the applicant may cure the deficiencies identified in the denial documentation and resubmit the application without paying an additional application fee, other than a fee for actual costs incurred by the municipality. Notwithstanding Subsection (d), the municipality shall approve or deny the revised completed application after a denial not later than the 90th day after the date the municipality receives the completed revised application. The municipality's review of the revised application is limited to the deficiencies cited in the denial documentation.
Cite this article: FindLaw.com - Texas Local Government Code - LOC GOV'T § 284.154. Municipal Review Process - last updated January 01, 2024 | https://codes.findlaw.com/tx/local-government-code/loc-gov-t-sect-284-154/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)