The person responsible for the drilling of a geotechnical hole for which a report is required under ORS 537.880 must have:

(1) A current monitoring well constructor's license as specified in rules adopted by the Water Resources Commission;

(2) A current water supply well constructor's license as specified in rules adopted by the commission;

(3) A current certificate of registration as a geologist issued under ORS 672.505 to 672.705; or

(4) A current certificate of registration as an engineer issued under ORS 672.002 to 672.325.

Cite this article: FindLaw.com - Oregon Revised Statutes Water Resources: Irrigation, Drainage, Flood Control, Reclamation § 537.885 - last updated January 01, 2018 | https://codes.findlaw.com/or/title-45-water-resources-irrigation-drainage-flood-control-reclamation/or-rev-st-sect-537-885/


FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.

Was this helpful?

Thank you. Your response has been sent.

Copied to clipboard