Current as of January 01, 2023 | Updated by Findlaw Staff
(1)(a) A public agency may not divide a public works project into more than one contract for the purpose of avoiding compliance with ORS 279C.800 to 279C.870.
(b) When the Commissioner of the Bureau of Labor and Industries determines that a public agency has divided a public works project into more than one contract for the purpose of avoiding compliance with ORS 279C.800 to 279C.870, the commissioner shall issue an order compelling compliance.
(c) In making determinations under this subsection, the commissioner shall consider:
(A) The physical separation of the project structures;
(B) The timing of the work on project phases or structures;
(C) The continuity of project contractors and subcontractors working on project parts or phases;
(D) The manner in which the public agency and the contractors administer and implement the project;
(E) Whether a single public works project includes several types of improvements or structures; and
(F) Whether the combined improvements or structures have an overall purpose or function.
(2) If a project is a public works of the type described in ORS 279C.800 (6)(a)(B) or (C), the commissioner shall divide the project, if appropriate, after applying the considerations set forth in subsection (1)(c) of this section to separate the parts of the project that include funds of a public agency or that will be occupied or used by a public agency from the parts of the project that do not include funds of a public agency and that will not be occupied or used by a public agency. If the commissioner divides the project, any part of the project that does not include funds of a public agency and that will not be occupied or used by a public agency is not subject to ORS 279C.800 to 279C.870.
(3) If a project includes parts that are owned by a public agency and parts that are owned by a private entity, the commissioner shall divide the project, if appropriate, after applying the considerations set forth in subsections (1)(c) and (2) of this section to separate the parts of the project that are public works from the parts of the project that are not public works. If the commissioner divides the project, parts of the project that are not public works are not subject to ORS 279C.800 to 279C.870.
Cite this article: FindLaw.com - Oregon Revised Statutes Public Facilities, Contracting and Insurance § 279C.827 - last updated January 01, 2023 | https://codes.findlaw.com/or/title-26-public-facilities-contracting-and-insurance/or-rev-st-sect-279c-827/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)