(A) A mechanic's lien for furnishing materials arises under sections 1311.01 to 1311.22 of the Revised Code only if the materials are:
(1) Furnished with the intent, as evidenced by the contract of sale, the delivery order, delivery to the site by the claimant or at the claimant's direction, or by other evidence, that the materials be used in the course of the improvement with which the lien arises;
(2) Incorporated in the improvement or consumed as normal wastage in the course of the improvement;
(3) Specifically fabricated for incorporation in the improvements and not readily resalable in the ordinary course of the fabricator's business even if not actually incorporated in the improvement;
(4) Used for the improvement or for the operation of machinery or equipment used in the course of the improvement and not remaining in the improvement, subject to diminution by the salvage value of those materials; or
(5) Tools or machinery used on the particular improvement, subject to division (C) of this section.
(B) The delivery of materials to the site of the improvement, whether or not by the claimant, creates a conclusive presumption that the materials were used in the course of the improvement or were incorporated into the improvement.
(C) A mechanics' lien for furnishing tools or machinery which arises under division (A)(5) of this section is limited to either of the following:
(1) If the tools or machinery are rented, the lien is for the reasonable rental value for the period of actual use and any reasonable period of nonuse taken into account in the rental contract.
(2) If the tools or machinery are purchased, the lien is for the price, but the lien only arises if the tools or machinery were purchased for use in the course of the particular improvement and have no substantial value to the purchaser after the completion of the improvement on which they were used.
(D) All of the deliveries or the sales, or both, by a material supplier of materials, including tools and machinery to or for an improvement, as ordered or purchased by an owner, original contractor, or subcontractor, shall give rise to one mechanics' lien for the unpaid portion of the sales to that owner, original contractor, or subcontractor. Nothing in this division shall prohibit the filing of more than one lien if a material supplier sold materials to more than one owner, original contractor, or subcontractor for the same improvement.
Cite this article: FindLaw.com - Ohio Revised Code Title XIII. Commercial Transactions § 1311.12 - last updated January 01, 2024 | https://codes.findlaw.com/oh/title-xiii-commercial-transactions/oh-rev-code-sect-1311-12/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)