1. Except as otherwise provided in subsection 2, not later than 30 days after the date on which a contractor receives notice of a constructional defect pursuant to NRS 40.645, the contractor shall forward a copy of the notice by certified mail, return receipt requested, to the last known address of each subcontractor, supplier or design professional whom the contractor reasonably believes is responsible for a defect specified in the notice.
2. If a contractor does not provide notice as required pursuant to subsection 1, the contractor may not commence an action against the subcontractor, supplier or design professional related to the constructional defect unless the contractor demonstrates that, after making a good faith effort, the contractor was unable to identify the subcontractor, supplier or design professional whom the contractor believes is responsible for the defect within the time provided pursuant to subsection 1.
3. Not later than 30 days after receiving notice from the contractor pursuant to this section, the subcontractor, supplier or design professional shall inspect the alleged constructional defect in accordance with NRS 40.6462 and provide the contractor with a written statement indicating:
(a) Whether the subcontractor, supplier or design professional has elected to repair the defect for which the contractor believes the subcontractor, supplier or design professional is responsible; and
(b) If the subcontractor, supplier or design professional elects to repair the defect, an estimate of the length of time required for the repair, and at least two proposed dates on and times at which the subcontractor, supplier or design professional is able to begin making the repair.
4. If a subcontractor, supplier or design professional elects to repair the constructional defect, the contractor or claimant may hold the subcontractor liable for any repair which does not eliminate the defect.
Cite this article: FindLaw.com - Nevada Revised Statutes Title 3. Remedies; Special Actions and Proceedings § 40.646. Notice of defect to be forwarded by contractor to subcontractor, supplier or design professional; effect of failure to forward notice; inspection of alleged defect; election to repair - last updated January 01, 2021 | https://codes.findlaw.com/nv/title-3-remedies-special-actions-and-proceedings/nv-rev-st-40-646/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)