1. If a subcontractor and another subcontractor or supplier enter into a subcontract for a public work, the subcontractor may withhold as retainage not more than 5 percent from the amount of any progress payment due under a subcontract which is made before 50 percent of the work has been completed under the subcontract.
2. After 50 percent of the work required by the subcontractor or supplier has been performed, the subcontractor shall pay any additional progress payments due under the subcontract without withholding any additional retainage if, in the opinion of the subcontractor, satisfactory progress is being made in the work under the subcontract. The payment must be equal to that paid by the contractor to the subcontractor for the work performed or supplies provided by his or her subcontractor or supplier. If the subcontractor continues to withhold retainage from remaining progress payments:
(a) If the subcontractor does not withhold any amount pursuant to NRS 338.600:
(1) The subcontractor may not withhold more than 2.5 percent of the amount of any progress payment; and
(2) Before withholding any amount pursuant to subparagraph (1), the subcontractor must pay to the subcontractor or supplier 50 percent of the amount of any retainage that was withheld from progress payments pursuant to subsection 1; or
(b) If the subcontractor withholds any amount pursuant to NRS 338.600:
(1) The subcontractor may not withhold more than 5 percent of the amount of any progress payment; and
(2) The subcontractor may continue to retain the amount of any retainage that was withheld from progress payments pursuant to subsection 1.
3. If the subcontractor receives a payment of interest earned on the retainage or an amount withheld from a progress payment, the subcontractor shall, within 10 days after receiving the money, pay to each of his or her subcontractors or suppliers that portion of the interest received from the contractor which is attributable to the retainage or amount withheld from a progress payment by the subcontractor to his or her subcontractor or supplier.
4. If, pursuant to subsection 4 of NRS 338.555, the contractor pays to the subcontractor the portion of any retainage withheld by the contractor pursuant to NRS 338.555 for the portion of the work which has been performed by the subcontractor, the subcontractor must pay to the subcontractor's subcontractors and suppliers the portion of any retainage withheld by the subcontractor pursuant to this section for the portion of the work.
Cite this article: FindLaw.com - Nevada Revised Statutes Title 28. Public Works and Planning § 338.595. Amounts withheld as retainage; payment of interest - last updated January 01, 2025 | https://codes.findlaw.com/nv/title-28-public-works-and-planning/nv-rev-st-338-595/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)