Any claim for any labor, material, or supply furnished for an improvement, upon which a suit is not commenced within one year after completion and acceptance of the project, is barred as a lien or claim against the contractor and the contractor's surety and any right of setoff or counterclaim may be enforced in any court in this state against the governing body, the contractor, or the contractor's surety. This chapter does not bar the right of any person who has furnished any labor, supply, or material to any subcontractor to enforce the claim against the subcontractor.
Cite this article: FindLaw.com - North Dakota Century Code Title 48. Public Buildings § 48-01.2-12. Claims--When barred as liens against contractor and surety - last updated January 01, 2024 | https://codes.findlaw.com/nd/title-48-public-buildings/nd-cent-code-sect-48-01-2-12/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)