(1) If electric facilities providers that have provided cost estimates to a new large customer are unable to reach agreement as to which electric facilities provider can provide electric service facilities at the least cost, an independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110, shall determine which electric facilities provider can extend its line to the new large customer at the least cost. The cost of those engineering services must be paid equally by the electric facilities providers involved.
(2) If electric facilities providers proposing to provide service to a subdivision do not agree on the location of a vector, as provided in 69-5-113(1), an independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110, shall determine the location of a vector. The cost of those engineering services must be paid equally by the electric facilities providers involved.
(3) If electric facilities providers having lines near the premises of a new consumer do not agree if a line has capacity to serve the premises, an independent consultant engineer agreeable to both electric facilities providers or, in the event of failure of the electric facilities providers to agree on a consultant engineer, an independent consultant engineer selected by the district court having jurisdiction, as provided in 69-5-110, shall determine if a line has capacity to serve the premises. The cost of those engineering services must be paid equally by the electric facilities providers involved.
Cite this article: FindLaw.com - Montana Title 69. Public Utilities and Carriers § 69-5-114. Review by independent consultant - last updated January 01, 2024 | https://codes.findlaw.com/mt/title-69-public-utilities-and-carriers/mt-st-69-5-114/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)