A public contractor shall not be considered to be working beyond contract time if the delay is caused by an accident or casualty produced by physical cause which is not preventable by human foresight, i.e., any of the misadventures termed an “act of God”.
Cite this article: FindLaw.com - Montana Title 18. Public Contracts § 18-2-312. Excusable delays - last updated January 01, 2024 | https://codes.findlaw.com/mt/title-18-public-contracts/mt-st-18-2-312/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)