Subdivision 1. Applicability. This section applies to a request by the owner of the large energy infrastructure facility to modify any provision or condition of a site or route permit issued by the commission, including the following:
(1) upgrades or rebuilds an existing electric line and associated facilities to a voltage capable of operating between 100 kilovolts and 300 kilovolts that does not result in significant changes in the human and environmental impact of the facility; or
(2) repowers or refurbishes a large electric power generating plant, a large wind energy conversion system, a solar energy generating system, or an energy storage system that increases the efficiency of the system, provided the project does not increase the developed area within the permitted site or increase the nameplate capacity of the facility's most recent interconnection agreement. For a large electric power generating plant, an increase in efficiency is a reduction in the amount of British thermal units required to produce a kilowatt hour of electricity at the facility.
Subd. 2. Application. A person that seeks authorization to amend a large energy infrastructure facility must apply to the commission. The application must be in writing and must (1) describe the alteration to be made or the amendment sought, and (2) explain why the request meets the eligibility criteria under subdivision 1. The application must describe any changes to the environmental impacts evaluated by the commission as part of the initial permit approval. If there are significant changes to the environmental impacts evaluated by the commission as part of the initial permit approval, environmental review must be conducted pursuant to the applicable requirements ofMinnesota Rules, chapter 4410, andparts 7849.1000to7849.2100.
Subd. 3. Notice. The commission must mail notice that the application was received to the persons on the general list and to the persons on the project contact list, if a project list exists.
Subd. 4. Public comment. The commission must provide at least a ten-day period for interested persons to submit comments on the application or to request that the matter be brought to the commission for consideration. The applicant may respond to submitted comments within seven days of the date the comment period closes.
Subd. 5. Timing. Within 30 days of the date the applicant responds to submitted comments under subdivision 4, the commission must decide whether to authorize the permit amendment, bring the matter to the commission for consideration, or determine that the application requires a permitting decision under another section in this chapter.
Subd. 6. Decision. The commission may authorize an amendment but impose reasonable conditions on the approval. The commission must notify the applicant in writing of the commission's decision and send a copy of the decision to any person who requested notification or filed comments on the application.
Subd. 7. Local review. For a large electric power generating plant or high-voltage transmission line that was not issued a permit by the commission, the owner or operator of the nonpermitted facility may seek approval of a project listed under subdivision 1 from the local unit of government if the facility qualifies for standard review undersection 216I.07or local review undersection 216I.08.
Cite this article: FindLaw.com - Minnesota Statutes Utilities (Ch. 216-216H) § 216I.09. Permit amendments - last updated January 01, 2025 | https://codes.findlaw.com/mn/utilities-ch-216-216h/mn-st-sect-216i-09/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)