(a) In order to establish a lien under this subtitle, a person entitled to a lien shall file proceedings in the circuit court for the county where the land or any part of the land is located within 180 days after the work has been finished or the materials furnished. The proceedings shall be commenced by filing with the clerk, the following:
(1) A petition to establish the mechanic's lien, which shall set forth at least the following:
(i) The name and address of the petitioner;
(ii) The name and address of the owner;
(iii) The nature or kind of work done or the kind and amount of materials furnished, the time when the work was done or the materials furnished, the name of the person for whom the work was done or to whom the materials were furnished, and the amount or sum claimed to be due, less any credit recognized by the petitioner;
(iv) A description of the land, including a statement whether part of the land is located in another county, and a description adequate to identify the building; and
(v) If the petitioner is a subcontractor, facts showing that the notice required under § 9-104 of this subtitle was properly mailed or served upon the owner, or, if so authorized, posted on the building. If the lien is sought to be established against two or more buildings on separate lots or parcels of land owned by the same person, the lien will be postponed to other mechanics' liens unless the petitioner designates the amount he claims is due him on each building;
(2) An affidavit by the petitioner or some person on his behalf, setting forth facts upon which the petitioner claims he is entitled to the lien in the amount specified; and
(3) Either original or sworn, certified, or photostatic copies of material papers or parts thereof, if any, which constitute the basis of the lien claim, unless the absence thereof is explained in the affidavit.
(b) The clerk shall docket the proceedings as an action in equity, and all process shall issue out of and all pleadings shall be filed in the one action.
Cite this article: FindLaw.com - Maryland Code, Real Property § 9-105 - last updated January 01, 2025 | https://codes.findlaw.com/md/real-property/md-code-real-prop-sect-9-105/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)