Current as of January 01, 2023 | Updated by FindLaw Staff
A. No contracts for the construction, alteration, or repair of any public works executed in conformity with this Part shall provide that the state or any of its agencies, boards, or subdivisions or any other public entity letting such a contract may withhold payment of more than ten percent of the contract price on projects of less than five hundred thousand dollars, and five percent of the contract price on projects of five hundred thousand dollars or more until the expiration of forty-five days after the recordation of formal acceptance of such work, or notice of default by the contractor or subcontractor. Such provision for withholding of payment shall in no way change or affect the liability of the letting agency or of the contractor, subcontractor, or their sureties.
B. (1) All public works contracts shall contain a clause stating that any punch list generated during a construction project shall include the cost estimates for the particular items of work the design professional has developed based on the mobilization, labor, material, and equipment costs of correcting each punch list item. The design professional shall retain his working papers used to determine the punch list items cost estimates should the matter be disputed later. The contracting agency shall not withhold from payment more than the value of the punch list. Punch list items completed shall be paid upon the expiration of the forty-five day lien period.
(2) If the public entity occupies or uses the public works, the following shall apply:
(a) The punch list shall be furnished to the contractor within ten days of substantial completion, as defined in R.S. 38:2241.1.
(b) Within fourteen days of providing the punch list to the contractor, the punch list may be amended by the design professional or the public entity.
(3) The provisions of this Section shall not be subject to waiver, nor shall these provisions apply to the Department of Transportation and Development.
C. Notwithstanding any provision of law to the contrary, a public entity letting a public works construction contract for a flood protection project or for an integrated coastal protection project as defined in R.S. 49:214.2, as per the terms of the contract, may withhold liquidated damages from any payments or monies otherwise due to the contractor, taking into consideration all granted time extensions, after the expiration of the forty-five day period set forth in R.S. 38:2242(B).
Cite this article: FindLaw.com - Louisiana Revised Statutes Tit. 38, § 2248. Provisions for withholding payment; effect on liability of contractor or agency; punch list; liquidated damages - last updated January 01, 2023 | https://codes.findlaw.com/la/revised-statutes/la-rev-stat-tit-38-sect-2248/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)