(1) Except for a utility as defined under KRS 278.010(9) that has been granted a certificate of public convenience and necessity prior to April 15, 2002, no utility shall begin the construction of a facility for the generation of electricity capable of generating in aggregate more than ten megawatts (10MW) without having first obtained a site compatibility certificate from the commission.
(2) An application for a site compatibility certificate shall include the submission of a site assessment report as prescribed in KRS 278.708(3) and (4), except that a utility which proposes to construct a facility on a site that already contains facilities capable of generating ten megawatts (10MW) or more of electricity shall not be required to comply with setback requirements established pursuant to KRS 278.704(3). A utility may submit and the commission may accept documentation of compliance with the National Environmental Policy Act (NEPA) rather than a site assessment report.
(3) The commission may deny an application filed pursuant to, and in compliance with, this section. The commission may require reasonable mitigation of impacts disclosed in the site assessment report including planting trees, changing outside lighting, erecting noise barriers, and suppressing fugitive dust, but the commission shall, in no event, order relocation of the facility.
(4) The commission may also grant a deviation from any applicable setback requirements on a finding that the proposed facility is designed and located to meet the goals of this section and KRS 224.10-280, 278.010, 278.212, 278.214, 278.218, and 278.700 to 278.716 at a distance closer than those provided by the applicable setback requirements.
(5) Nothing contained in this section shall be construed to limit a utility's exemption provided under KRS 100.324.
(6) Unless specifically stated otherwise, for the purposes of this section, “utility” has the same meaning as in KRS 278.010(3)(a) or (9).
Cite this article: FindLaw.com - Kentucky Revised Statutes Title XXIV. Public Utilities § 278.216.Site compatibility certificate; site assessment report; commission action on application - last updated January 01, 2025 | https://codes.findlaw.com/ky/title-xxiv-public-utilities/ky-rev-st-sect-278-216/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)