Sec. 58. (a) This section applies to a construction contract entered into by the department and a contractor after June 30, 2005.
(b) The department may not include in a contract, or in any specifications or other documents that are a part of or incorporated in a contract, a provision that prohibits a contractor from receiving, or restricts the contractor in receiving, reasonable compensation or reasonable expenses directly related to unforeseen conditions encountered during the construction project as a result of:
(1) a conflict with the facilities of a utility (as defined in IC 8-1-9-2(a)); or
(2) delays due to the relocation of utility facilities;
that differ materially from the affected utilities or utility relocations specified in the contract documents.
Cite this article: FindLaw.com - Indiana Code Title 8. Utilities and Transportation § 8-23-9-58 - last updated January 02, 2024 | https://codes.findlaw.com/in/title-8-utilities-and-transportation/in-code-sect-8-23-9-58/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)