Sec. 7. The certification requirements of this chapter do not apply to a person that:
(1) constructs an electric generating facility primarily for that person's own use and not for the primary purpose of producing electricity, heat, or steam for sale to or for the public for compensation;
(2) constructs an alternate energy production facility, cogeneration facility, or a small hydro facility that complies with the limitations set forth in IC 8-1-2.4-5;
(3) is a municipal utility, including a joint agency created under IC 8-1-2.2-8, and installs an electric generating facility that has a capacity of ten thousand (10,000) kilowatts or less;
(4) is a public utility and:
(A) installs a clean energy project described in IC 8-1-8.8-2(2) that is approved by the commission and that:
(i) uses a clean energy resource described in IC 8-1-37-4(a)(1), IC 8-1-37-4(a)(2), or IC 8-1-37-4(a)(5); and
(ii) has a nameplate capacity of not more than fifty thousand (50,000) kilowatts; and
(B) uses a contractor that:
(i) is subject to Indiana unemployment taxes; and
(ii) is selected by the public utility through bids solicited in a competitive procurement process;
in the engineering, procurement, or construction of the project; or
(5) is:
(A) a corporation organized under IC 8-1-13;
(B) a corporation organized under IC 23-17 that is an electric cooperative and that has at least one (1) member that is a corporation organized under IC 8-1-13; or
(C) a:
(i) surviving corporation that remains after a merger of two (2) or more corporations under IC 8-1-17.5; or
(ii) successor corporation that is formed from a consolidation of two (2) or more corporations under IC 8-1-17.5;
that installs an electric generating facility that has a capacity of ten thousand (10,000) kilowatts or less.
However, a person described in this section shall, nevertheless, be required to report to the commission the proposed construction of such a facility before beginning construction of the facility.
Cite this article: FindLaw.com - Indiana Code Title 8. Utilities and Transportation § 8-1-8.5-7 - last updated January 02, 2024 | https://codes.findlaw.com/in/title-8-utilities-and-transportation/in-code-sect-8-1-8-5-7/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)