Current as of January 02, 2024 | Updated by Findlaw Staff
Sec. 16. (a) In addition to the review of the continued appropriateness of an environmental compliance plan under section 15 of this chapter, the commission shall, at the request of a public utility, conduct an ongoing review of the cost and implementation of the public utility's approved environmental compliance plan. The public utility shall submit to the commission:
(1) each year; or
(2) at other times the commission and the public utility agree on;
a progress report that includes any information the commission may require.
(b) If the commission approves the cost and implementation of the part of the environmental compliance plan under review, then, absent fraud, concealment, or gross mismanagement, the approval forecloses subsequent challenges to:
(1) the recovery in rates of those costs; and
(2) if the public utility is allowed by law to earn a return on the public utility's investment, the addition to the fair value of the public utility's property of the fair value of a completed capital project, or portion of a capital project, that:
(A) is constructed and consists of:
(i) new systems, equipment, or facilities; or
(ii) modifications to existing systems, equipment, or facilities; and
(B) is part of the environmental compliance plan implementation approved by the commission;
up to the amount approved under section 7(2) or 12 of this chapter, whichever is applicable. The public utility may not recover costs in excess of the cost estimate approved by the commission under section 7(2) or 12 of this chapter, whichever is applicable, unless the commission finds that the additional costs were necessary and prudent.
(c) If the commission does not issue an order disapproving all or part of the implementation of the part of the environmental compliance plan under review within six (6) months of the commencement of the action seeking the commission's approval, the commission shall be considered to have approved all of the implementation of that part of the environmental compliance plan unless the commission issues an order extending the time for such review.
Cite this article: FindLaw.com - Indiana Code Title 8. Utilities and Transportation § 8-1-28-16 - last updated January 02, 2024 | https://codes.findlaw.com/in/title-8-utilities-and-transportation/in-code-sect-8-1-28-16/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)