Sec. 17. (a) A contract for road or street work must contain a provision for the timely payment of claims made by the contractor.
(b) Each contract must provide for final payment within one hundred twenty (120) days after final acceptance and completion of the contract. Final payment may not be made on any amount that is in dispute, but final payment may be made on that part of a contract or those amounts that are not in dispute.
(c) For each day after one hundred twenty (120) days, the board shall pay to the contractor interest for late payment of money due to the contractor. However, interest may not be paid for those days that the delay in payment is not directly attributable to the board. The annual percentage rate of interest that the board shall pay on the unpaid balance is twelve percent (12%).
Cite this article: FindLaw.com - Indiana Code Title 36. Local Government § 36-1-12-17 - last updated January 02, 2024 | https://codes.findlaw.com/in/title-36-local-government/in-code-sect-36-1-12-17/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)