Sec. 10. (a) If the state department receives corrections to a plan in response to a notice sent under section 8(b)(2)(B) of this chapter, and any time the state department receives corrections to a notice under subdivision (2) thereafter, the state department shall do one (1) of the following:
(1) Not later than ten (10) business days, or fifteen (15) business days if agreed upon by the applicant and the state department, after receiving the corrections, send notice to the applicant that the corrected plans as submitted have been approved for a construction permit. The state department shall, not later than the next business day after the date that notice is sent to the applicant, provide the applicant with a construction permit.
(2) Not later than ten (10) business days, or fifteen (15) business days if agreed upon by the applicant and the state department, after receiving the corrections, send notice to the applicant that a construction permit will not be issued until the applicant submits additional corrections. However, if the applicant does not receive the notice within the period specified in this subdivision:
(A) the application is approved as submitted; and
(B) the state department shall, not later than the eleventh or sixteenth business day after the date that the corrections were received by the state department, whichever is applicable, provide the applicant with a construction permit.
(b) A review under this section is limited to:
(1) the corrections required by the state department under the notice sent under section 8(b)(2)(B) of this chapter or subsection (a)(2); and
(2) any revisions made to the plan that have not been reviewed, regardless of whether those revisions were requested under section 8(b)(2)(B) of this chapter or subsection (a)(2).
All other parts of a project not directly related to corrections or revisions described in subdivision (1) or (2), including previously completed corrections or revisions that the state department has already accepted, are considered approved for a construction permit and may not be included in subsequent notice requests sent under this section.
Cite this article: FindLaw.com - Indiana Code Title 16. Health § 16-19-3.5-10 - last updated January 02, 2024 | https://codes.findlaw.com/in/title-16-health/in-code-sect-16-19-3-5-10/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)