Sec. 16. (a) A review authority to which a construction plan is submitted must make a preliminary determination whether the construction plan is substantially complete before the end of:
(1) the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site; or
(2) the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site.
(b) If a review authority to which a construction plan is submitted under subsection (a):
(1) makes a preliminary determination that the construction plan is substantially complete; and
(2) notifies the project site owner of its favorable preliminary determination;
before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, the project site owner may submit a notice of intent letter including the information required by 327 IAC 15-5-5 or the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.
(c) If a review authority to which a construction plan for a small or very small construction activity site or a large construction activity site is submitted under subsection (a) does not notify the project site owner before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination as to whether the construction plan is substantially complete, the project site owner may submit a notice of intent letter including the information required by 327 IAC 15-5-5 or the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.
(d) If a review authority to which a construction plan is submitted under subsection (a) notifies the project site owner before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination that the construction plan is not substantially complete, the project site owner may not submit a notice of intent letter until the review authority makes a conclusive favorable determination concerning the construction plan under 327 IAC 15-5, the general permit, or the applicable ordinance of the MS4 community.
(e) If a review authority to which a construction plan is submitted under subsection (a):
(1) makes a preliminary determination that the construction plan is substantially complete; and
(2) makes a conclusive unfavorable determination concerning the construction plan under 327 IAC 15-5, the general permit, or the applicable ordinance of the MS4 community;
the land disturbing activities of the construction project must stop when the review authority notifies the project site owner of the review authority's conclusive unfavorable determination concerning the construction plan.
Cite this article: FindLaw.com - Indiana Code Title 13. Environment § 13-18-27-16 - last updated January 01, 2026 | https://codes.findlaw.com/in/title-13-environment/in-code-sect-13-18-27-16/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)