Learn About The Law
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Current as of January 01, 2026 | Updated by Findlaw Staff
(a) Any activity in the wetlands requires a permit from the Department except the activity or activities exempted by this chapter and no permit may be granted unless the county or municipality having jurisdiction has first approved the activity in question by zoning procedures provided by law.
(b) The Secretary shall consider the following factors prior to issuance of any permit:
(1) Environmental impact, including but not limited to, likely destruction of wetlands and flora and fauna; impact of the site preparation on tidal ebb and flow and the otherwise normal drainage of the area in question, especially as it relates to flood control; impact of the site preparation and proposed activity on land erosion; effect of site preparation and proposed activity on the quality and quantity of tidal waters, surface, ground and subsurface water resources and other resources;
(2) Aesthetic effect, such as the impact on scenic beauty of the surrounding area;
(3) The number and type of public and private supporting facilities required and the impact of such facilities on all factors listed in this subsection;
(4) Effect on neighboring land uses, including but not limited to, public access to tidal waters, recreational areas and effect on adjacent residential and agricultural areas;
(5) State, county and municipal comprehensive plans for the development and/or conservation of their areas of jurisdiction;
(6) Economic effect, including the number of jobs created and the income which will be generated by the wages and salaries of the jobs in relation to the amount of land required, and the amount of tax revenues potentially accruing to the state, county and local governments.
(c) The Secretary may require a bond in an amount and with surety and conditions sufficient to secure compliance with the conditions and limitations, if any, set forth in the permit. The particular amount and the particular conditions of the bond required shall be consistent with and in furtherance of the purposes of this chapter. The Secretary shall state for the record, the basis for the bonding requirements imposed with each permit granted. In the event of a breach of any condition of any such bond, the Attorney General may institute an action in Superior Court upon such bond and prosecute the same to judgment and execution.
Cite this article: FindLaw.com - Delaware Code Title 7. Conservation § 6604. Permit required - last updated January 01, 2026 | https://codes.findlaw.com/de/title-7-conservation/de-code-sect-7-6604/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)