(1) When a court is determining the necessity of taking private land or nonfederal public land for the installation of a pipeline, the court shall require the pipeline company:
(a) To show that the particular land lies within a route which is the most direct route practicable;
(b) To post a bond with the court equal to double the amount which the court determines to be the estimated cost of restoring the affected land to the same or as good a condition as it was in prior to the installation of the pipeline; except that the pipeline company may elect to deposit cash, negotiable bonds of the United States government or any political subdivision of this state, or negotiable certificates of deposit of any bank or other savings institution organized or transacting business in the United States equal to double such cost. Said bond shall not be released until the court is satisfied that the condemned land has been restored to the same or as good a condition as existed prior to the installation of the pipeline, and, if the affected land is productive agricultural land, that the soil which sustains the agricultural activity has been restored so as to provide for the continuation of such agricultural activity, and that any damages awarded by the court have been paid. If the condemned land is adjacent to or in proximity of the boundary of federal land of comparable use, such bond shall not be released until the company has restored the land to at least the same reclamation standards and meets such other standards and requirements for such federal land as required by the laws, rules, and regulations of the federal government.
(c) To consider existing utility rights-of-way before any new routes are taken if the land to be condemned is adjacent to existing utility rights-of-way.
(2) When land is condemned for a pipeline, the determination of the amount of compensation to be received by the landowner shall reflect consideration of the fact that the condemned land is to be restored as required in this section.
Cite this article: FindLaw.com - Colorado Revised Statutes Title 38. Property Real and Personal § 38-1-101.5. Necessity of taking land for pipelines - last updated January 01, 2025 | https://codes.findlaw.com/co/title-38-property-real-and-personal/co-rev-st-sect-38-1-101-5/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)