(a) A distribution borrower that is a member of a power supply borrower, with a total utility plant of $500 million or more must provide a load forecast in support of any request for RUS financial assistance. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the approved load forecast of its power supply borrower. The distribution borrower's load forecast must be prepared pursuant to the load forecast work plan of its power supply borrower.
(b) A distribution borrower that is a member of a power supply borrower which is itself a member of another power supply borrower that has a total utility plant of $500 million or more must provide a load forecast in support of any request for RUS financial assistance. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the load forecast of its power supply borrower. The distribution borrower's load forecast must be prepared pursuant to the load forecast work plan of the power supply borrower with total utility plant in excess of $500 million.
(c) A distribution borrower that is a member of a power supply borrower with a total utility plant of less than $500 million must provide a load forecast that meets the requirements of this subpart in support of an application for any RUS loan or loan guarantee that exceeds $3 million or 5 percent of total utility plant, whichever is greater. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the load forecast of its power supply borrower.
(d) A distribution borrower with a total utility plant of less than $500 million and that is unaffiliated with a power supply borrower must provide a load forecast that meets the requirements of this subpart in support of an application for any RUS loan or loan guarantee which exceeds $3 million or 5 percent of total utility plant, whichever is greater.
(e) A distribution borrower with a total utility plant of $500 million or more must provide a load forecast in support of any request for RUS financing assistance. The borrower must also maintain a load forecast work plan. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the load forecast of its power supply borrower.
Cite this article: FindLaw.com - Code of Federal Regulations Title 7. Agriculture § 7.1710.203 Requirement to prepare a load forecast—distribution borrowers - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-7-agriculture/cfr-sect-7-1710-203/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)