Borrower Designation ____
Date Prepared ____
Ratings on form are:
0: Unsatisfactory—no records
1: Unsatisfactory—corrective action needed
2: Acceptable, but should be improved—see attached recommendations
3: Satisfactory—no additional action required at this time
N/A: Not applicable
PART I—TRANSMISSION and DISTRIBUTION FACILITIES
1. Substations (Transmission and Distribution)
a. Safety, Clearance, Code Compliance—Rating: ____
b. Physical Condition: Structure, Major Equipment, Appearance—Rating: ____
c. Inspection Records Each Substation—Rating: ____
d. Oil Spill Prevention—Rating: ____
2. Transmission Lines
a. Right–of–Way: Clearing, Erosion, Appearance, Intrusions—Rating: ____
b. Physical Condition: Structure, Conductor, Guying—Rating: ____
c. Inspection Program and Records—Rating: ____
3. Distribution Lines—Overhead
a. Inspection Program and Records—Rating: ____
b. Compliance with Safety Codes: Clearances—Rating: ____
Compliance with Safety Codes: Foreign Structures—Rating: ____
Compliance with Safety Codes: Attachments—Rating: ____
c. Observed Physical Condition from Field Checking: Right–of–Way—Rating: ____
Observed Physical Condition from Field Checking: Other—Rating: ____
4. Distribution—Underground Cable
a. Grounding and Corrosion Control—Rating: ____
b. Surface Grading, Appearance—Rating: ____
c. Riser Poles: Hazards, Guying, Condition—Rating: ____
5. Distribution Line Equipment: Conditions and Records
a. Voltage Regulators—Rating: ____
b. Sectionalizing Equipment—Rating: ____
c. Distribution Transformers—Rating: ____
d. Pad Mounted Equipment—Safety: Locking, Dead Front, Barriers—Rating: ____
Pad Mounted Equipment—Appearance: Settlement, Condition—Rating: ____
e. Kilowatt-hour and Demand Meter Reading and Testing—Rating: ____
PART II—OPERATION AND MAINTENANCE
6. Line Maintenance and Work Order Procedures
a. Work Planning and Scheduling—Rating: ____
b. Work Backlogs: Right–of–Way Maintenance—Rating: ____
Work Backlogs: Poles—Rating: ____
Work Backlogs: Retirement of Idle Services—Rating: ____
Work Backlogs: Other—Rating: ____
7. Service Interruptions
a. Average Annual Hours/Consumer by Cause (Complete for each of the previous 5 years)
1. Power Supplier ____
2. Major Storm ____
3. Scheduled ____
4. All Other ____
5. Total ____
Rating: ____
b. Emergency Restoration Plan—Rating:____
8. Power Quality
General Freedom from Complaints—Rating:____
9. Loading and Load Balance
a. Distribution Transformer Loading—Rating:____
b. Load Control Apparatus—Rating:____
c. Substation and Feeder Loading—Rating:____
10. Maps and Plant Records
a. Operating Maps: Accurate and Up–to–Date—Rating:____
b. Circuit Diagrams—Rating:____
c. Staking Sheets—Rating:____
PART III—ENGINEERING
11. System Load Conditions and Losses
a. Annual System Loses, ____%—Rating:____
b. Annual Load Factor, ____%—Rating:____
c. Power Factor at Monthly Peak, ____%—Rating:____
d. Ratio of Individual Substation Peak kW to kVA, ____—Rating:____
12. Voltage Conditions
a. Voltage Surveys—Rating:____
b. Substation Transformer Output Voltage Spread—Rating:____
13. Load Studies and Planning
a. Long Range Engineering Plan—Rating:____
b. Construction Work Plan—Rating:____
c. Sectionalizing Study—Rating:____
d. Load Data for Engineering Studies—Rating:____
e. Load Forecasting Data—Rating:____
f. Energy Efficiency and Conservation Program quality assurance compliance—
Rating:———
PART IV—OPERATION AND MAINTENANCE BUDGETS
For Previous 2 Years:
Normal Operation—Actual $____
Normal Maintenance—Actual $____
Total—Actual $____
For Present Year:
Normal Operation—Budget $____
Normal Maintenance—Budget $____
Total—Budget $____
For Future 3 Years:
Normal Operation—Budget $____
Normal Maintenance—Budget $____
Additional (Deferred) Maintenance—Budget $____
Total—Budget $____
14. Budgeting:
Adequacy of Budgets For Needed Work—Rating:____
15. Date Budget Discussed with Board of Directors ________
Remarks: ____
EXPLANATORY NOTES
Item No.____ Comments ____
Rated by ________ Title ____ Date ____
Reviewed by ____ Manager ____ Date ____
Reviewed by ____ RUS GFR ____ Date ____
Cite this article: FindLaw.com - Code of Federal Regulations Title 7. Agriculture 7 CFR Pt. 1730, Subpt. B, App. A Appendix A to Subpart B of Part 1730—Review Rating Summary, RUS Form 300 - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-7-agriculture/cfr-pt-7-1730-subpt-b-app-a/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)