As prescribed in 42.709–7, use the following clause:
Penalties for Unallowable Costs (SEP 2021)
(a) Definition. Proposal, as used in this clause, means either—
(1) A final indirect cost rate proposal submitted by the Contractor after the expiration of its fiscal year which—
(i) Relates to any payment made on the basis of billing rates; or
(ii) Will be used in negotiating the final contract price; or
(2) The final statement of costs incurred and estimated to be incurred under the Incentive Price Revision clause (if applicable), which is used to establish the final contract price.
(b) Contractors which include unallowable indirect costs in a proposal may be subject to penalties. The penalties are prescribed in 10 U.S.C. 2324 or 41 U.S.C. chapter 43, as applicable, which is implemented in section 42.709 of the Federal Acquisition Regulation (FAR).
(c) The Contractor shall not include in any proposal any cost that is unallowable, as defined in subpart 2.1 of the FAR, or an executive agency supplement to the FAR.
(d) If the Contracting Officer determines that a cost submitted by the Contractor in its proposal is expressly unallowable under a cost principle in the FAR, or an executive agency supplement to the FAR, that defines the allowability of specific selected costs, the Contractor shall be assessed a penalty equal to—
(1) The amount of the disallowed cost allocated to this contract; plus
(2) Simple interest, to be computed—
(i) On the amount the Contractor was paid (whether as a progress or billing payment) in excess of the amount to which the Contractor was entitled; and
(ii) Using the applicable rate effective for each six-month interval prescribed by the Secretary of the Treasury pursuant to Pub.L. 92–41 (85 Stat. 97).
(e) If the Contracting Officer determines that a cost submitted by the Contractor in its proposal includes a cost previously determined to be unallowable for that Contractor, then the Contractor will be assessed a penalty in an amount equal to two times the amount of the disallowed cost allocated to this contract.
(f) Determinations under paragraphs (d) and (e) of this clause are final decisions within the meaning of 41 U.S.C. chapter 71, Contract Disputes.
(g) Pursuant to the criteria in FAR 42.709–6, the Contracting Officer may waive the penalties in paragraph (d) or (e) of this clause.
(h) Payment by the Contractor of any penalty assessed under this clause does not constitute repayment to the Government of any unallowable cost which has been paid by the Government to the Contractor.
(End of clause)
Cite this article: FindLaw.com - Code of Federal Regulations Title 48. Federal Acquisition Regulations System 48.52.242-3 Penalties for Unallowable Costs - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-48-federal-acquisition-regulations-system/cfr-48-52-242-3/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)