(a) Plant clearance officers should review and accept, or return for correction, inventory disposal schedules within 10 days following receipt from a contractor. Schedules that are completed in accordance with the instructions for Standard Form 1428 should be accepted.
(b) Plant clearance officers shall—
(1) Use Standard Form 1423 to verify, in accordance with agency procedures, accepted schedules within 20 days following acceptance;
(2) Require the contractor to correct any discrepancies found during verification;
(3) Require the contractor to correct any failure to complete predisposal requirements of the contract; and
(4) Provide the contractor disposition instructions for property identified on an acceptable inventory disposal schedule within 120 days. A failure to provide timely disposition instructions may entitle the contractor to an equitable adjustment.
(c) The contractor may request the plant clearance officer's approval to remove the Government property from an inventory schedule.
(1) Plant clearance officers should approve removal of Government property from an inventory schedule when—
(i) The contractor wishes to purchase a contractor-acquired or contractor-produced item at unit acquisition cost and credit the contract;
(ii) The contractor is able to return unused property to the supplier at fair market value and credit the contract (less, if applicable, a reasonable restocking fee that is consistent with the supplier's customary practices);
(iii) The Government has authorized the contractor to use the property on another Government contract; or
(iv) The contractor has requested continued use of the Government property, and the contracting officer has authorized its retention and further use.
(2) If the screening process (see 45.602–3) has not begun, the plant clearance officer shall adjust the schedule or return the schedule to the contractor for correction. If screening has begun, the plant clearance officer shall promptly notify the activity performing the screening that the items should be removed from the screening process.
Cite this article: FindLaw.com - Code of Federal Regulations Title 48. Federal Acquisition Regulations System 48.45.602-1 Inventory disposal schedules - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-48-federal-acquisition-regulations-system/cfr-48-45-602-1/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs