(a)(1) Insert the clause at 52.232–16, Progress Payments, in—
(i) Solicitations that may result in contracts providing for progress payments based on costs; and
(ii) Fixed-price contracts under which the Government will provide progress payments based on costs.
(2) If advance agency approval has been given in accordance with 32.501–1, the contracting officer may substitute a different customary rate for other than small business concerns for the progress payment and liquidation rate indicated.
(3) If an unusual progress payment rate is approved for the prime contractor (see 32.501–2), substitute the approved rate for the customary rate in paragraphs (a)(1), (a)(6), and (b) of the clause.
(4) If the liquidation rate is changed from the customary progress payment rate (see 32.503–8 and 32.503–9), substitute the new rate for the rate in paragraphs (a)(1), (a)(6), and (b) of the clause.
(5) If an unusual progress payment rate is approved for a subcontract (see 32.504(c) and 32.501–2), modify paragraph (j)(6) of the clause to specify the new rate, the name of the subcontractor, and that the new rate shall be used for that subcontractor in lieu of the customary rate.
(b) If the contractor is a small business concern, use the clause with its Alternate I.
(c) If the contract is a letter contract, use the clause with its Alternate II.
(d) If the contractor is not a small business concern, and progress payments are authorized under an indefinite-delivery contract, basic ordering agreement, or their equivalent, use the clause with its Alternate III.
(e) If the nature of the contract necessitates separate progress payment rates for portions of work that are clearly severable and accounting segregation would be maintained (e.g., annual production requirements), describe the application of separate progress payment rates in a supplementary special provision within the contract. The contractor must submit separate progress payment requests and subsequent invoices for the severable portions of work in order to maintain accounting integrity.
Cite this article: FindLaw.com - Code of Federal Regulations Title 48. Federal Acquisition Regulations System 48.32.502-4 Contract clauses - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-48-federal-acquisition-regulations-system/cfr-48-32-502-4/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)