(a) If the contracting officer has determined that an exception applies because the cost of certain domestic construction material is unreasonable, in accordance with section 25.604, then the contracting officer shall apply evaluation factors to the offer incorporating the use of such foreign construction material as follows:
(1) Use an evaluation factor of 25 percent, applied to the total offered price of the contract, if foreign manufactured construction material is incorporated in the offer based on an exception for unreasonable cost of comparable domestic construction material requested by the offeror.
(2) In addition, use an evaluation factor of 20 percent applied to the cost of foreign unmanufactured construction material incorporated in the offer based on an exception for unreasonable cost of comparable domestic unmanufactured construction material requested by the offeror.
(3) Total evaluated price = offered price + (.25 x offered price, if (a)(1) applies) + (.20 x cost of foreign unmanufactured construction material, if (a)(2) applies).
(b) If the solicitation specifies award on the basis of factors in addition to cost or price, apply the evaluation factors as specified in paragraph (a) of this section and use the evaluated price in determining the offer that represents the best value to the Government.
(c) Unless paragraph (b) applies, if two or more offers are equal in price, the contracting officer must give preference to an offer that does not include foreign construction material excepted at the request of the offeror on the basis of unreasonable cost.
(d) Offerors also may submit alternate offers based on use of equivalent domestic construction material to avoid possible rejection of the entire offer if the Government determines that an exception permitting use of a particular foreign construction material does not apply.
(e) If the contracting officer awards a contract to an offeror that proposed foreign construction material not listed in the applicable clause in the solicitation (paragraph (b)(3) of 52.225–21, or paragraph (b)(3) of 52.225–23), the contracting officer must add the excepted materials to the list in the contract clause.
Cite this article: FindLaw.com - Code of Federal Regulations Title 48. Federal Acquisition Regulations System 48.25.605 Evaluating offers of foreign construction material - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-48-federal-acquisition-regulations-system/cfr-48-25-605/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)