Learn About The Law
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Current as of January 02, 2025 | Updated by Findlaw Staff
(a) When a contractor is unable to deliver urgent and critical items because of a work stoppage at its facility, the contracting officer, before removing any items from the facility, shall—
(i) Before initiating any action, contact the labor advisor to obtain the opinion of the national office of the Federal Mediation and Conciliation Service or other mediation agency regarding the effect movement of the items would have on labor negotiations. Normally removals will not be made if they will adversely affect labor negotiations.
(ii) Upon the recommendation of the labor advisor, provide a written request for removal of the material to the cognizant contract administration office. Include in the request the information specified at PGI 222.101–4(a)(ii).
(iii) With the assistance of the labor advisor or the commander of the contract administration office, attempt to have both the management and the labor representatives involved agree to shipment of the material by normal means.
(iv) If agreement for removal of the needed items cannot be reached following the procedures in paragraphs (a) (i) through (iii) of this subsection, the commander of the contract administration office, after obtaining approval from the labor advisor, may seek the concurrence of the parties to the dispute to permit movement of the material by military vehicles with military personnel. On receipt of such concurrences, the commander may proceed to make necessary arrangements to move the material.
(v) If agreement for removal of the needed items cannot be reached following any of the procedures in paragraphs (a) (i) through (iv) of this subsection, refer the matter to the labor advisor with the information required by 222.101–3–70(b). If the labor advisor is unsuccessful in obtaining concurrence of the parties for the movement of the material and further action to obtain the material is deemed necessary, refer the matter to the agency head. Upon review and verification that the items are urgently or critically needed and cannot be moved with the consent of the parties, the agency head, on a nondelegable basis, may order removal of the items from the facility.
Cite this article: FindLaw.com - Code of Federal Regulations Title 48. Federal Acquisition Regulations System 48.22.101-4 222.101–4 Removal of items from contractors' facilities affected by work stoppages - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-48-federal-acquisition-regulations-system/cfr-48-222-101-4/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)