The lease will be issued subject to the following terms and conditions:
(a) Lease term. The term of your lease includes the initial partial year in which it is issued, plus 30 additional full years. The lease will terminate on December 31 of the final year of the lease term. You may submit an application for renewal under § 2805.14(g).
(b) Rent. You must pay rent as specified in:
(1)Section 2806.54, if your lease is for solar energy development; or
(2)Section 2806.64, if your lease is for wind energy development.
(c) POD. You must submit, within 2 years of the lease issuance date, a POD that:
(1) Is consistent with the development schedule and other requirements in the POD template posted at http://www.blm.gov; and
(2) Addresses all pre-development and development activities.
(d) Cost recovery. You must pay the reasonable costs for the BLM or other Federal agencies to review and approve your POD and to monitor your lease. To expedite review of your POD and monitoring of your lease, you may notify BLM in writing that you are waiving paying reasonable costs and are electing to pay the full actual costs incurred by the BLM.
(e) Performance and reclamation bond.
(1) For Solar Energy Development, you must provide a bond in the amount of $10,000 per acre prior to written approval to proceed with ground disturbing activities.
(2) For Wind Energy Development, you must provide a bond in the amount of $10,000 per authorized turbine less than 1 MW in nameplate capacity or $20,000 per authorized turbine equal or greater than 1 MW in nameplate capacity prior to written approval to proceed with ground disturbing activities.
(3) For testing and monitoring sites authorized under a development lease, you must provide a bond in the amount of $2,000 per site prior to receiving written approval to proceed with ground disturbing activities.
(4) The BLM will adjust the solar and wind energy development bond amounts every 10 years using the change in the IPD–GDP for the preceding 10–year period rounded to the nearest $100. This 10–year average will be adjusted at the same time as the Per Acre Rent Schedule for linear rights-of-way under § 2806.22.
(f) Assignments. You may assign your lease under § 2807.21, and if an assignment is approved, the BLM will not make any changes to the lease terms or conditions, as provided for by § 2807.21(e) except for modifications required under § 2805.15(e).
(g) Due diligence of operations. You must start construction within 5 years and begin generation of electricity no later than 7 years from the date of lease issuance, as specified in your approved POD. A request for an extension may be granted for up to 3 years with a show of good cause and approval by the BLM.
Cite this article: FindLaw.com - Code of Federal Regulations Title 43. Public Lands: Interior § 43.2809.18 What terms and conditions apply to leases? - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-43-public-lands-interior/cfr-sect-43-2809-18/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)