Each State must submit a HIT PAPD update or a HIT IAPD no later than 60 days after the occurrence of project changes including but not limited to any of the following:
(a) A projected cost increase of $100,000 or more.
(b) A schedule extension of more than 60 days for major milestones.
(c) A significant change in planning approach or implementation approach, or scope of activities beyond that approved in the HIT planning advance planning document or the HIT implementation advance planning document.
(d) A change in implementation concept or a change to the scope of the project.
(e) A change to the approved cost allocation methodology.
Cite this article: FindLaw.com - Code of Federal Regulations Title 42. Public Health § 42.495.340 As-needed HIT PAPD update and as-needed HIT IAPD update requirements - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-42-public-health/cfr-sect-42-495-340/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)