[As stated in § 63.8826, you must comply with the applicable General Provisions requirements according to the following table:] |
|||
|---|---|---|---|
|
Citation |
Requirement |
Applies to subpart MMMMM |
Explanation |
|
§ 63.1 |
Initial applicability determination; applicability after standard established; permit requirements; extensions; notifications |
Yes. |
|
|
§ 63.2 |
Definitions |
Yes |
Additional definitions are found in § 63.8830. |
|
§ 63.3 |
Units and abbreviations |
Yes. |
|
|
§ 63.4 |
Prohibited activities; compliance date; circumvention, severability |
Yes. |
|
|
§ 63.5 |
Construction/reconstruction applicability; applications; approvals |
Yes. |
|
|
§ 63.6(a) |
Compliance with standards and maintenance requirements-applicability |
Yes. |
|
|
§ 63.6(b)(1)-(4) |
Compliance dates for new or reconstructed sources |
Yes |
§ 63.8786 specifies compliance dates. |
|
§ 63.6(b)(5) |
Notification if commenced construction or reconstruction after proposal |
Yes. |
|
|
§ 63.6(b)(6) |
[Reserved] |
Yes. |
|
|
§ 63.6(b)(7) |
Compliance dates for new or reconstructed area sources that become major |
Yes |
§ 63.8786 specifies compliance dates. |
|
§ 63.6(c)(1)-(2) |
Compliance dates for existing sources |
Yes |
§ 63.8786 specifies compliance dates. |
|
§ 63.6(c)(3)-(4) |
[Reserved] |
Yes. |
|
|
§ 63.6(c)(5) |
Compliance dates for existing area sources that become major |
Yes |
§ 63.8786 specifies compliance dates. |
|
§ 63.6(d) |
[Reserved] |
Yes. |
|
|
§ 63.6(e)(1) |
Operation and maintenance requirements |
Yes. |
|
|
§ 63.6(e)(2) |
[Reserved] |
Yes. |
|
|
§ 63.6(e)(3) |
Startup, shutdown, and malfunction plans |
Yes |
Only applies to new or reconstructed flame lamination affected sources. |
|
§ 63.6(f)(1) |
Compliance except during SSM |
Yes |
Only applies to new or reconstructed flame lamination affected sources. |
|
§ 63.6(f)(2)-(3) |
Methods for determining compliance |
Yes. |
|
|
§ 63.6(g) |
Use of an alternative nonopacity emission standard |
Yes. |
|
|
§ 63.6(h) |
Compliance with opacity/visible emission standards |
No |
Subpart MMMMM does not specify opacity or visible emission standards. |
|
§ 63.6(i) |
Extension of compliance with emission standards |
Yes. |
|
|
§ 63.6(j) |
Presidential compliance exemption |
Yes. |
|
|
§ 63.7(a)(1)-(2) |
Performance test dates |
Yes |
Except for loop slitter affected sources as specified in § 63.8798(a). |
|
§ 63.7(a)(3) |
Administrator's section 114 authority to require a performance test |
Yes. |
|
|
§ 63.7(b) |
Notification of performance test and rescheduling |
Yes. |
|
|
§ 63.7(c) |
Quality assurance program and site-specific test plans |
Yes. |
|
|
§ 63.7(d) |
Performance testing facilities |
Yes. |
|
|
§ 63.7(e)(1) |
Conditions for conducting performance tests |
Yes. |
|
|
§ 63.7(f) |
Use of an alternative test method |
Yes. |
|
|
§ 63.7(g) |
Performance test data analysis, recordkeeping, and reporting |
Yes. |
|
|
§ 63.7(h) |
Waiver of performance tests |
Yes. |
|
|
§ 63.8(a)(1)-(2) |
Applicability of monitoring requirements |
Yes |
Unless otherwise specified, all of § 63.8 applies only to new or reconstructed flame lamination sources. Additional monitoring requirements for these sources are found in §§ 63.8794(f) and (g) and 63.8804. |
|
§ 63.8(a)(3) |
[Reserved] |
Yes. |
|
|
§ 63.8(a)(4) |
Monitoring with flares |
No |
Subpart MMMMM does not refer directly or indirectly to § 63.11. |
|
§ 63.8(b) |
Conduct of monitoring and procedures when there are multiple effluents and multiple monitoring systems |
Yes. |
|
|
§ 63.8(c)(1)-(3) |
Continuous monitoring system (CMS) operation and maintenance |
Yes |
Applies as modified by § 63.8794(f) and (g). |
|
§ 63.8(c)(4) |
Continuous monitoring system requirements during breakdown, out-of-control, repair, maintenance, and high-level calibration drifts |
Yes |
Applies as modified by § 63.8794(g). |
|
§ 63.8(c)(5) |
Continuous opacity monitoring system (COMS) minimum procedures |
No |
Subpart MMMMM does not have opacity or visible emission standards. |
|
§ 63.8(c)(6) |
Zero and high level calibration checks |
Yes |
Applies as modified by § 63.8794(f). |
|
§ 63.8(c)(7)-(8) |
Out-of-control periods, including reporting |
Yes. |
|
|
§ 63.8(d)-(e) |
Quality control program and CMS performance evaluation |
No |
Applies as modified by § 63.8794(f) and (g). |
|
§ 63.8(f)(1)-(5) |
Use of an alternative monitoring method |
Yes. |
|
|
§ 63.8(f)(6) |
Alternative to relative accuracy test |
No |
Only applies to sources that use continuous emissions monitoring systems (CEMS). |
|
§ 63.8(g) |
Data reduction |
Yes |
Applies as modified by § 63.8794(g). |
|
§ 63.9(a) |
Notification requirements—applicability |
Yes. |
|
|
§ 63.9(b) |
Initial notifications |
Yes |
Except § 63.8816(c) requires new or reconstructed affected sources to submit the application for construction or reconstruction required by § 63.9(b)(1)(iii) in lieu of the initial notification. |
|
§ 63.9(c) |
Request for compliance extension |
Yes. |
|
|
§ 63.9(d) |
Notification that a new source is subject to special compliance requirements |
Yes. |
|
|
§ 63.9(e) |
Notification of performance test |
Yes. |
|
|
§ 63.9(f) |
Notification of visible emissions/opacity test |
No |
Subpart MMMMM does not have opacity or visible emission standards. |
|
§ 63.9(g)(1) |
Additional CMS notifications—date of CMS performance evaluation |
Yes. |
|
|
§ 63.9(g)(2) |
Use of COMS data |
No |
Subpart MMMMM does not require the use of COMS. |
|
§ 63.9(g)(3) |
Alternative to relative accuracy testing |
No |
Applies only to sources with CEMS. |
|
§ 63.9(h) |
Notification of compliance status |
Yes. |
|
|
§ 63.9(i) |
Adjustment of submittal deadlines |
Yes. |
|
|
§ 63.9(j) |
Change in previous information |
Yes. |
|
|
§ 63.9(k) |
Electronic reporting procedures |
Yes |
Only as specified in § 63.9(j). |
|
§ 63.10(a) |
Recordkeeping/reporting applicability |
Yes. |
|
|
§ 63.10(b)(1) |
General recordkeeping requirements |
Yes |
§§ 63.8820 and 63.8822 specify additional recordkeeping requirements. |
|
§ 63.10(b)(2)(i)-(xi) |
Records related to startup, shutdown, and malfunction periods and CMS |
Yes |
Only applies to new or reconstructed flame lamination affected sources. |
|
§ 63.10(b)(2)(xii) |
Records when under waiver |
Yes. |
|
|
§ 63.10(b)(2)(xiii) |
Records when using alternative to relative accuracy test |
No |
Applies only to sources with CEMS. |
|
§ 63.10(b)(2)(xiv) |
All documentation supporting initial notification and notification of compliance status |
Yes |
|
|
§ 63.10(b)(3) |
Recordkeeping requirements for applicability determinations |
Yes. |
|
|
§ 63.10(c) |
Additional recordkeeping requirements for sources with CMS |
Yes |
Applies as modified by § 63.8794(g). |
|
§ 63.10(d)(1) |
General reporting requirements |
Yes |
§ 63.8818 specifies additional reporting requirements. |
|
§ 63.10(d)(2) |
Performance test results |
Yes |
|
|
§ 63.10(d)(3) |
Opacity or visible emissions observations |
No |
Subpart MMMMM does not specify opacity or visible emission standards. |
|
§ 63.10(d)(4) |
Progress reports for sources with compliance extensions |
Yes. |
|
|
§ 63.10(d)(5) |
Startup, shutdown, and malfunction reports |
Yes |
Only applies to new or reconstructed flame lamination affected sources. |
|
§ 63.10(e)(1) |
Additional CMS reports—general |
Yes |
Applies as modified by § 63.8794(g). |
|
§ 63.10(e)(2)(i) |
Results of CMS performance evaluations |
Yes |
Applies as modified by § 63.8794(g). |
|
§ 63.10(e)(2) |
Results of continuous opacity monitoring systems performance evaluations |
No |
Subpart MMMMM does require the use of COMS. |
|
§ 63.10(e)(3) |
Excess emissions/CMS performance reports |
Yes |
Only applies to new or reconstructed flame lamination affected sources. |
|
§ 63.10(e)(4) |
Continuous opacity monitoring system data reports |
No |
Subpart MMMMM does not require the use of COMS. |
|
§ 63.10(f) |
Recordkeeping/reporting waiver |
Yes |
|
|
§ 63.11. |
Control device requirements—applicability |
No |
Facilities subject to subpart MMMMM do not use flares as control devices. |
|
§ 63.12 |
State authority and delegations |
Yes |
§ 63.8828 lists those sections of subparts MMMMM and A that are not delegated. |
|
§ 63.13 |
Addresses |
Yes. |
|
|
§ 63.14 |
Incorporation by reference |
Yes |
Subpart MMMMM does not incorporate any material by reference. |
|
§ 63.15 |
Availability of information/confidentiality. |
Yes. |
Cite this article: FindLaw.com - Code of Federal Regulations Title 40. Protection of Environment 40 CFR Pt. 63, Subpt. MMMMM, Tbl. 7 Table 7 to Subpart MMMMM of Part 63—Applicability of General Provisions to Subpart MMMMM - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-40-protection-of-environment/cfr-pt-40-63-subpt-mmmmm-tbl-7/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)