As required in § 63.7833(a), you must demonstrate continuous compliance with the emission and opacity limits according to the following table:
|
For . . . |
You must demonstrate continuous compliance by . . . |
|---|---|
|
1. Each windbox exhaust stream at an existing sinter plant |
a. Maintaining emissions of particulate matter at or below 0.4 lb/ton of product sinter; and |
|
b. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
2. Each windbox exhaust stream at a new sinter plant |
a. Maintaining emissions of particulate matter at or below 0.3 lb/ton of product sinter; and |
|
b. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
3. Each discharge end at an existing sinter plant |
a. Maintaining emissions of particulate matter from one or more control devices at or below 0.02 gr/dscf; and |
|
b. Maintaining the opacity of secondary emissions that exit any opening in the building or structure housing the discharge end at or below 20 percent (6-minute average); and |
|
|
c. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
4. Each discharge end at a new sinter plant |
a. Maintaining emissions of particulate matter from one or more control devices at or below 0.01 gr/dscf; and |
|
b. Maintaining the opacity of secondary emissions that exit any opening in the building or structure housing the discharge end at or below 10 percent (6-minute average); and |
|
|
c. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
5. Each sinter cooler at an existing sinter plant |
a. Maintaining the opacity of emissions that exit any sinter cooler at or below 10 percent (6-minute average); and |
|
b. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
6. Each sinter cooler at a new sinter plant |
a. Maintaining emissions of particulate matter at or below 0.1 gr/dscf; and |
|
b. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
7. Each casthouse at an existing blast furnace |
a. Maintaining emissions of particulate matter from a control device at or below 0.01 gr/dscf; and |
|
b. Maintaining the opacity of secondary emissions that exit all openings in the casthouse or structure housing the casthouse at or below 20 percent (6-minute average); and |
|
|
c. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
8. Each casthouse at a new blast furnace |
a. Maintaining emissions of particulate matter from a control device at or below 0.003 gr/dscf; and |
|
b. Maintaining the opacity of secondary emissions that exit all openings in the casthouse or structure housing the casthouse at or below 15 percent (6-minute average); and |
|
|
c. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
9. Each BOPF at a new or existing BOPF shop |
a. Maintaining emissions of particulate matter from the primary control system for a BOPF with a closed hood system at or below 0.03 gr/dscf; and |
|
b. Maintaining emissions of particulate matter from the primary control system for a BOPF with an open hood system at or below 0.02 gr/dscf for an existing BOPF shop or 0.01 gr/dscf for a new BOPF shop; and |
|
|
c. Maintaining emissions of particulate matter from a control device applied solely to secondary emissions from a BOPF at or below 0.01 gr/dscf for an existing BOPF shop or 0.0052 gr/dscf for a new BOPF shop; and |
|
|
d. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
10. Each hot metal transfer, skimming, and desulfurization operation at a new or existing BOPF shop |
a. Maintaining emissions of particulate matter from a control device at or below 0.01 gr/dscf at an existing BOPF or 0.003 gr/dscf for a new BOPF; and |
|
b. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
11. Each ladle metallurgy operation at a new or existing BOPF shop |
a. Maintaining emissions of particulate matter from a control device at or below 0.01 gr/dscf at an existing BOPF shop or 0.004 gr/dscf for a new BOPF shop; and |
|
b. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
12. Each existing BOPF shop |
a. Maintaining the opacity of secondary emissions that exit any opening in the BOPF shop or other building housing the BOPF shop or shop operation at or below 20 percent (3-minute average); and |
|
b. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
13. Each new BOPF shop |
a. Maintaining the opacity (for any set of 6-minute averages) of secondary emissions that exit any opening in the BOPF shop or other building housing a bottom-blown BOPF or shop operation at or below 10 percent, except that one 6-minute period greater than 10 percent but no more than 20 percent may occur once per steel production cycle; and |
|
b. Maintaining the opacity (for any set of 3-minute averages) of secondary emissions that exit any opening in the BOPF shop or other building housing a top-blown BOPF or shop operation at or below 10 percent, except that one 3-minute period greater than 10 percent but less than 20 percent may occur once per steel production cycle; and |
|
|
c. Conducting subsequent performance tests at the frequencies specified in § 63.7821. |
|
|
14. Each BOPF Group at an existing BOPF shop |
a. Maintaining emissions of mercury from the collection of BOPF Group control devices at or below 0.00026 lb/ton steel scrap input to the BOPF; and |
|
b. If demonstrating compliance through performance testing, conducting subsequent performance tests at the frequencies specified in § 63.7821; and |
|
|
c. If demonstrating compliance through § 63.7791(c), (d), or (e), maintaining records pursuant to § 63.7842(e). |
|
|
15. Each BOPF Group at a new BOPF shop |
a. Maintaining emissions of mercury from the collection of BOPF Group control devices at or below 0.000081 lb/ton steel scrap input to the BOPF; and |
|
b. If demonstrating compliance through performance testing, conducting subsequent performance tests at the frequencies specified in § 63.7821; and |
|
|
c. If demonstrating compliance through § 63.7791(c), (d), or (e), maintaining records pursuant to § 63.7842(e). |
Cite this article: FindLaw.com - Code of Federal Regulations Title 40. Protection of Environment 40 CFR Pt. 63, Subpt. FFFFF, Tbl. 3 TABLE 3 TO SUBPART FFFFF OF PART 63—CONTINUOUS COMPLIANCE WITH EMISSION AND OPACITY LIMITS - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-40-protection-of-environment/cfr-pt-40-63-subpt-fffff-tbl-3/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)