As stated in § 63.2386(a), (b), and (f), you must submit compliance reports and startup, shutdown, and malfunction reports according to the following table:
|
You must submit a(n) . . . |
The report must contain . . . |
You must submit the report . . . |
|---|---|---|
|
1. Compliance report or Periodic Report |
a. The information specified in § 63.2386(c), (d), (e). If you had a SSM during the reporting period and you took actions consistent with your SSM plan, the report must also include the information in § 63.10(d)(5)(i) except as specified in item 1.e of this table; AND |
Semiannually, and it must be postmarked or electronically submitted by January 31 or July 31, in accordance with § 63.2386(b). |
|
b. The information required by 40 CFR part 63, subpart TT, UU, or H, as applicable, for pumps, valves, and sampling connections; AND |
See the submission requirement in item 1.a of this table. |
|
|
c. The information required by § 63.999(c); AND |
See the submission requirement in item 1.a of this table. |
|
|
d. The information specified in § 63.1066(b) including: Notification of inspection, inspection results, requests for alternate devices, and requests for extensions, as applicable |
See the submission requirement in item 1.a of this table. |
|
|
e. Beginning no later than the compliance dates specified in § 63.2342(e), the requirement to include the information in § 63.10(d)(5)(i) no longer applies. |
||
|
2. Immediate SSM report if you had a SSM that resulted in an applicable emission standard in the relevant standard being exceeded, and you took an action that was not consistent with your SSM plan |
a. The information required in § 63.10(d)(5)(ii) |
i. Except as specified in item 2.a.ii of this table, by letter within 7 working days after the end of the event unless you have made alternative arrangements with the permitting authority (§ 63.10(d)(5)(ii)). |
|
ii. Beginning no later than the compliance dates specified in § 63.2342(e), item 2.a.i of this table no longer applies. |
Cite this article: FindLaw.com - Code of Federal Regulations Title 40. Protection of Environment 40 CFR Pt. 63, Subpt. EEEE, Tbl. 11 Table 11 to Subpart EEEE of Part 63—Requirements for Reports - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-40-protection-of-environment/cfr-pt-40-63-subpt-eeee-tbl-11/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)