These schedules have been reviewed and determined to be acceptable by EPA.
|
Affected facilities at the following MWC sites |
City, State |
Increment 1 |
Increment 2 |
Increment 3 |
Increment 4 |
Increment 5 |
|---|---|---|---|---|---|---|
|
Submit final control plan |
Award contracts |
Begin on-site construction |
Complete on-site construction |
Final compliancec |
||
|
Stanislaus Resource Recovery Facility |
Crows Landing, California |
January 11, 1999 |
01/19/00 |
05/19/00 |
11/19/00 |
12/19/00 |
|
Southeast Resource Recovery Facility |
Long Beach, California |
January 11, 1999 |
04/30/99 |
10/31/99 |
04/30/00 |
12/19/00 |
|
All large MWC units |
Maine |
January 11, 1999 |
01/01/99 |
07/01/99 |
09/01/00 |
12/19/00 |
|
Baltimore Resco |
Baltimore, Maryland |
January 11, 1999 |
January 11, 1999 |
January 11, 1999 |
09/01/00 |
12/19/00 |
|
All large MWC units |
New Jerseyb |
January 11, 1999 |
05/18/99 |
11/14/99 |
11/19/00 |
12/19/00 |
|
American Ref-Fuel |
Delaware County, Pennsylvania |
11/01/98 |
05/18/99 |
11/14/99 |
11/19/00 |
12/19/00 |
|
Montenay Energy Resource |
Montgomery County, Pennsylvania |
11/01/98 |
05/18/99 |
11/14/99 |
11/19/00 |
12/19/00 |
|
I-95 Energy/Resource Recovery Facility |
Lorton, Virginia |
January 11, 1999 |
10/15/99 |
03/01/00 |
11/19/00 |
12/19/00 |
|
New Hanover County, Unit 3A |
Wilmington, North Carolina |
09/15/99 |
03/01/00 |
07/01/00 |
11/19/00 |
12/19/00 |
b This schedule applies to HC1 SO2, PM, Pb, Cd, CO, and NOX. However, owners and operators of large MWC units in New Jersey have the option of reserving the portion of their control plan that addresses NOX. Owners and operators must submit the reserved portion to EPA by December 15, 1999.
c The owner or operator of an affected facility that began construction, modification, or reconstruction after June 26, 1987 must achieve final compliance with the mercury and dioxins/furans limits within 1 year after promulgation of subpart FFF (i.e., by 11/12/99) or 1 year after permit issuance. Permit issuance is issuance of a revised construction permit or revised operating permit if a permit modification is required to retrofit controls. Final compliance must be achieved no later than December 19, 2000, even if the date “1 year after permit issuance” exceeds December 19, 2000.
Cite this article: FindLaw.com - Code of Federal Regulations Title 40. Protection of Environment 40 CFR Pt. 62, Subpt. FFF, Tbl. 6 Table 6 to Subpart FFF of Part 62—Site–Specific Compliance Schedules and Increments of Progress a] - last updated January 02, 2025 | https://codes.findlaw.com/cfr/title-40-protection-of-environment/cfr-pt-40-62-subpt-fff-tbl-6/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)