(a) You must obtain approval from the Regional Supervisor before you start producing from a reservoir within a well that has any portion of the completed interval less than 500 feet from a unit or lease line. Submit to BSEE the service fee listed in § 250.125, according to the instructions in § 250.126, and the supporting information, as listed in the table in § 250.1167, with your request. The Regional Supervisor will determine whether approval of your request will maximize ultimate recovery, avoid the waste of natural resources, or protect correlative rights. You do not need to obtain approval if the adjacent leases or units have the same unit, lease (record title and operating rights), and royalty interests as the lease or unit you plan to produce. You do not need to obtain approval if the adjacent block is unleased.
(b) You must notify the operator(s) of adjacent property(ies) that are within 500 feet of the completion, if the adjacent acreage is a leased block in the Federal OCS. You must provide the Regional Supervisor proof of the date of the notification. The operators of the adjacent properties have 30 days after receiving the notification to provide the Regional Supervisor letters of acceptance or objection. If an adjacent operator does not respond within 30 days, the Regional Supervisor will presume there are no objections and proceed with a decision. The notification must include:
(1) The well name;
(2) The rectangular coordinates (x, y) of the location of the top and bottom of the completion or target completion referenced to the North American Datum 1983, and the subsea depths of the top and bottom of the completion or target completion;
(3) The distance from the completion or target completion to the unit or lease line at its nearest point; and
(4) A statement indicating whether or not it will be a high-capacity completion having a perforated or open hole interval greater than 150 feet measured depth.
Cite this article: FindLaw.com - Code of Federal Regulations Title 30. Mineral Resources § 30.250.1156 What steps must I take to receive approval to produce within 500 feet of a unit or lease line? - last updated October 02, 2022 | https://codes.findlaw.com/cfr/title-30-mineral-resources/cfr-sect-30-250-1156/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)