(a) Initial planning and site selection phase. The NEPA procedures must be initiated as part of the planning and site selection phase of all new construction, expansion, and renovation projects and completed before the construction or renovation on the project can begin.
(b) Early consultation with OJP. As grantees identify proposed, new projects, the grantees must inform OJP and after consulting OJP's Program Guidance on Environmental Protection Requirements, must recommend to OJP whether:
(1) The proposed project meets the criteria of a categorical exclusion;
(2) An environmental assessment should be initiated;
(3) Because of the project size and/or anticipated environmental impacts, an environmental impact statement should be initiated.
(c) Design phase. Projects currently in the planning and design phase must complete the NEPA procedures and no further decisions or new commitments of resources can be made on these projects by the State or local entity that would either have an adverse impact on the environment or limit the choice of reasonable alternative sites.
(d) Prohibited pre-analysis activities. None of the following actions can be taken until the NEPA analysis is completed for the affected project:
(1) Starting construction;
(2) Accepting construction bids;
(3) Advertising for construction bids;
(4) Initiating the development of or approving final plans and specifications; or
(5) Purchasing property.
(e) Ongoing or completed construction projects. For grant-funded projects under construction, OJP will work with the States to determine what environmental analysis has been done, making every effort to limit disruption to projects under construction. For completed grant-funded projects, OJP will work with the States to determine whether those projects may pose continuing environmental problems. For example, NEPA issues may exist due to excessive noise, light pollution, excessive water consumption or draw down on an important stream, or adverse visual impact due to an inappropriate facade color in an environmentally scenic area. Consequently, performing an analysis for those VOI/TIS VOI/TIS projects for which construction is completed may still serve the useful purpose of determining the extent of a project's continuing adverse environmental impacts, and the feasibility of mitigation measures.
(f) Avoiding duplication of efforts. If an EA or EIS was completed on an original structure, any environmental research that was conducted at the time the original structure was being planned and is still relevant need not be duplicated in any required environmental impact analysis for proposed modifications or additions to that structure.
Cite this article: FindLaw.com - Code of Federal Regulations Title 28. Judicial Administration § 28.91.58 Timing of the environmental review process - last updated October 02, 2022 | https://codes.findlaw.com/cfr/title-28-judicial-administration/cfr-sect-28-91-58/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw's Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)