TVA shall pay a Contractor interest on the amount found to be due on a claim:
(a) From the date payment is due under the contract or the Contracting Officer receives the claim, whichever is later, until TVA makes payment;
(b) At the rate payable pursuant to section 12 of the Act on the date from which interest runs pursuant to paragraph (a) of this section.
Cite this article: FindLaw.com - Code of Federal Regulations Title 18. Conservation of Power and Water Resources § 18.1308.5 Interest - last updated October 03, 2022 | https://codes.findlaw.com/cfr/title-18-conservation-of-power-and-water-resources/cfr-sect-18-1308-5/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature or via Westlaw before relying on it for your legal needs.