Current as of January 01, 2025 | Updated by Findlaw Staff
(a) Notwithstanding any other provision of law, no notice of intention is required, and the commission shall issue its final decision on the application, as specified in Section 25523, within 12 months after the filing of the application for certification of the powerplant and related facility or facilities, or at any later time as is mutually agreed by the commission and the applicant, for any of the following:
(1) A thermal powerplant which will employ cogeneration technology, a thermal powerplantthat will employ natural gas-fired technology, or a solar thermal powerplant.
(2) A modification of an existing facility.
(3) A thermal powerplant which it is only technologically or economically feasible to site at or near the energy source.
(4) A thermal powerplant with a generating capacity of up to 100 megawatts.
(5) A thermal powerplant designed to develop or demonstrate technologies which have not previously been built or operated on a commercial scale. Such a research, development, or commercial demonstration project may include, but is not limited to, the use of renewable or alternative fuels, improvements in energy conversion efficiency, or the use of advanced pollution control systems. Such a facility may not exceed 300 megawatts unless the commission, by regulation, authorizes a greater capacity. Section 25524 does not apply to such a powerplant and related facility or facilities.
(b) Projects exempted from the notice of intention requirement pursuant to paragraph (1), (4), or (5) of subdivision (a) shall include, in the application for certification, a discussion of the applicant's site selection criteria, any alternative sites that the applicant considered for the project, and the reasons why the applicant chose the proposed site. That discussion shall not be required for cogeneration projects at existing industrial sites. The commission may also accept an application for a noncogeneration project at an existing industrial site without requiring a discussion of site alternatives if the commission finds that the project has a strong relationship to the existing industrial site and that it is therefore reasonable not to analyze alternative sites for the project.
Cite this article: FindLaw.com - California Code, Public Resources Code - PRC § 25540.6 - last updated January 01, 2025 | https://codes.findlaw.com/ca/public-resources-code/prc-sect-25540-6/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)