(a) An applicant for a geothermal powerplant may propose a site to be approved that will accommodate a potential maximum electric generating capacity in excess of the capacity being proposed for initial construction. In addition to the information concerning the initial powerplant and related facilities proposed for construction required pursuant to Section 25520, such application shall include all of the following, to the extent known:
(1) The number, type, and energy source of electric generating units which the site is proposed ultimately to accommodate and the maximum generating capacity for each unit.
(2) The projected installation schedule for each unit.
(3) The impact of the site, when fully developed, on the environment and public health and safety.
(4) The amount and sources of cooling water needed at the fully developed site.
(5) The general location and design of auxiliary facilities planned for each stage of development, including, but not limited to pipelines, transmission lines, waste storage and disposal facilites, 1 switchyards, and cooling ponds, lakes, or towers.
(6) Such other information relating to the design, operation, and siting of the facility as the commission may by regulation require.
(b) If an application is filed pursuant to subdivision (a) which proposes a site to be approved which will accommodate a potential maximum electric generating capacity in excess of the capacity being proposed for initial construction, the commission may, in its decision pursuant to subdivision (a) of Section 25540.3, either certify only the initial facility or facilities proposed for initial construction or may certify the initial facility or facilities and find the site acceptable for additional generating capacity of the type tentatively proposed. The maximum allowable amount and type of such additional capacity shall be determined by the commission.
If the decision includes a finding that a particular site is suitable to accommodate a particular additional generating capacity, the site shall be designated a potential multiple facility site. The commission may, in determining the acceptability of a potential multiple facility site, specify conditions or criteria necessary to ensure that future additional facilities will not exceed the limitations of the site.
Cite this article: FindLaw.com - California Code, Public Resources Code - PRC § 25540.3 - last updated January 01, 2025 | https://codes.findlaw.com/ca/public-resources-code/prc-sect-25540-3/
FindLaw Codes may not reflect the most recent version of the law in your jurisdiction. Please verify the status of the code you are researching with the state legislature before relying on it for your legal needs.
A free source of state and federal court opinions, state laws, and the United States Code. For more information about the legal concepts addressed by these cases and statutes, visit FindLaw’s Learn About the Law.
Get help with your legal needs
FindLaw’s Learn About the Law features thousands of informational articles to help you understand your options. And if you’re ready to hire an attorney, find one in your area who can help.
Search our directory by legal issue
Enter information in one or both fields (Required)